Difference between revisions of "1951 AHSME Problems/Problem 13"

(Solution)
m (Added category: Rate Problems)
 
(One intermediate revision by one other user not shown)
Line 11: Line 11:
  
 
[[Category:Introductory Algebra Problems]]
 
[[Category:Introductory Algebra Problems]]
 +
[[Category:Rate Problems]]
 +
{{MAA Notice}}

Latest revision as of 16:07, 18 July 2015

Problem

$A$ can do a piece of work in $9$ days. $B$ is $50\%$ more efficient than $A$. The number of days it takes $B$ to do the same piece of work is:

$\textbf{(A)}\ 13\frac {1}{2} \qquad\textbf{(B)}\ 4\frac {1}{2} \qquad\textbf{(C)}\ 6 \qquad\textbf{(D)}\ 3 \qquad\textbf{(E)}\ \text{none of these answers}$

Solution

Because $B$ is $50\%$ more efficient, he can do $1.5$ pieces of work in $9$ days. This is equal to 1 piece of work in $\textbf{(C)}\ 6$ days

See Also

1951 AHSC (ProblemsAnswer KeyResources)
Preceded by
Problem 12
Followed by
Problem 14
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
All AHSME Problems and Solutions

The problems on this page are copyrighted by the Mathematical Association of America's American Mathematics Competitions. AMC logo.png